Suppose that you are a foreman of a building construction. The project engineer assigned you to determine the needed number of workers for each phase of the construction. You know that if ten skilled men and sixteen unskilled men work together, they can complete a phase of the project in ten days. The same job can be done by thirty skilled men in 8 days. The project has nine phases. The daily wage of an unskilled worker is Php540 while the skilled worker is Php630. The completion of the project is 85 days. You will present the plan to the project engineer
 