Hi all,
The question is as follows:
Calculate the probability that the project will take longer than 13 weeks to complete:
There are 5 activities that are independent from one another, A, B, C, D, E
Activity Expected Duration
A 10
B 8
C 12
D 15
E 13
I have calculated the probabilities of completion using given variance and Z table as:
Activity Probability of completion in 13 weeks or under
A 0.9968
B 0.9999
C 0.8413
D 0.1190
E 0.2033
What is the probability that the project will take longer than 13 weeks to complete?
The question is as follows:
Calculate the probability that the project will take longer than 13 weeks to complete:
There are 5 activities that are independent from one another, A, B, C, D, E
Activity Expected Duration
A 10
B 8
C 12
D 15
E 13
I have calculated the probabilities of completion using given variance and Z table as:
Activity Probability of completion in 13 weeks or under
A 0.9968
B 0.9999
C 0.8413
D 0.1190
E 0.2033
What is the probability that the project will take longer than 13 weeks to complete?