    Deli Flow: make sure the process is able to meet the demand of the catering business.

    I believe the time needs to be shaved off by downtime, if one station is Toasting the sub @ 2m45s then the station after doing wrapping and etc isn't doing anything within that period. I just need a solid math solution to account for downtime I assume. :confused:
  2. N

    Deli Flow: make sure the process is able to meet the demand of the catering business.

    So far I've got: Current = 1 Sub p/ 600 Seconds | 1 Sub p/ 10 Minutes | 6 Sub p/ 1 Hour | 60 Subs @ 10 Hours Need = 1 Sub p/ 500 Seconds | 1 Sub p/ 8.33333 Minutes | 7.2 p/ 1 Hour | 72 Subs @ 10 Hours So, I need to I guess shave 100 seconds off the time to meet the new 75 subs per day quote...
  3. N

    Deli Flow: make sure the process is able to meet the demand of the catering business.

    I'm just stumped on where to go with it.. I get at the current rate 6 sandwiches can be made over a 10 hour shift resulting in 60 total. But, when it ask for a 25% increase bringing 60 to 75, I'm not sure how to work backwards and tie it all in. I'm just lost. Would love to know how this...
  4. N

    Deli Flow: make sure the process is able to meet the demand of the catering business.

    Anyone care to help with this? Scenario: Imagine you are a leader at a small deli. The owner of the deli, your supervisor, has decided to expand the business by beginning a catering service. In order for this venture to be successful, your supervisor asks you to overview your current process...