Hello the question reads.
"Site records indicate that this crew backfilled 3,520m3 of basement over a 3 week period working 5-days/week; 8-hours/day."
There is one Labour Foreman @$65.00 per hour, 4 Labours @$28.00, 1 Operator @$45.00.
There is one Backhoe @$145.00, one Roller @$95.00.
2 Questions
What was the productivity rate of the crew expressed as CREW.HOURS/m3
What was the productivity rate of the crew expressed as m3 / MAN.HOUR
Here is my work so far.
Crew Productivity:
3,520m3 / ( 15 days x 8 hours) = 29.3m3 per hour
Average Cost Per Worker
$222.00 per hour / 6 = $37.00 per man hour
Average Cost Per Equipment
$240.00 per hour / 2 = $120.00 per man hour
"Site records indicate that this crew backfilled 3,520m3 of basement over a 3 week period working 5-days/week; 8-hours/day."
There is one Labour Foreman @$65.00 per hour, 4 Labours @$28.00, 1 Operator @$45.00.
There is one Backhoe @$145.00, one Roller @$95.00.
2 Questions
What was the productivity rate of the crew expressed as CREW.HOURS/m3
What was the productivity rate of the crew expressed as m3 / MAN.HOUR
Here is my work so far.
Crew Productivity:
3,520m3 / ( 15 days x 8 hours) = 29.3m3 per hour
Average Cost Per Worker
$222.00 per hour / 6 = $37.00 per man hour
Average Cost Per Equipment
$240.00 per hour / 2 = $120.00 per man hour