Path analysis

Joined
May 12, 2019
Messages
189
From the table below:
*a network diagram showing the tasks in the project
• the tasks in the critical path of the project
• the minimum length of time required to complete the project
• the start and finish time for each task
• the allocation of tasks to a minimum number of groups
• a recommendation of when you can view at least three different tasks in action

1586904149402.png


My working: I have drawn out my network diagram, I have found the critical path to be A, D,E,G,H,I,J at 11 weeks
the minimum time required is 9 weeks via A, D,F,H,I,J,

for allocation please see my table below, but based on it I believe there need to be 3 groups. A recommendation for a time to view at least 3 projects at the same time is between 4-6weeks. More than happy to attach my diagram if needed
01234567891011
A1-------------D2------------------------------E3-----------------------------------------------G2------------------------------H2------------------------------I(0.5)J(0.5-----------------
B4----------------------------------------------------------------C3-----------------------------------------------
F3---------------------------------------------
 
I should have mentioned from the beginning this is a critical path analysis. I want to make sure my paths I have worked out are correct and my gnatt bar chart is also correct.
 