A team of copper miners planned to mine 1800 tons of ore during certain number of days. Due to technical difficulties in the one third of the planned number of days, the team was able to achieve an output of 20 tons less than the planned output . To make up for this, the team overachieved for the rest of the days by 20 tons . The end result was the team completed the task one day ahead of time. How many tons of ore did the team initially plan to mine per day (Tons)?
A) 50
B) 200
C) 150
D) 100
E) 250
I found it to be a time and work question .
Wa = Team work rate original
Wb = Work rate when technical glitch was found .
x = No of days it took for the team to originally complete the work .
Wa * x = 1800 --(i)
x/3 * Wb = ( Wa * x/3 ) - 20 ---(ii) the team was able to achieve an output of 20 tons less than the planned output
y = 1800 - ( tons covered in 1/3 Days by team at a work rate of Wb ) --(iii)
Wa * (x - x/3) = y + 20 --(iv) the team overachieved for the rest of the days by 20 tons
Wa * ( (x - 1) - x/3 ) + ( Wb x ) / 3 = 1800 --(v) The end result was the team completed the task one day ahead of time
(vi)-- Tons covered in x/3 days = Wb * x/3
We see that
Wb x = 5400 - Wa (2x -3)
Wb = ( 5400 - Wa ( 2x -3) ) / x
x/3 * Wb = ( Wa * x/3 ) - 20 ---(ii)
Substituting Wb in (ii)
1800 / ( 3 Wa) * ( 5400 / x - Wa ( 2x -3) / x ) = ( Wa x ) / 3 - 20
600 / Wa * 5400 / x - ( 600/Wa * (Wa * ( 2x -3 ) ) / x ) = Wa x / 3 - 20
Substituting 1800 / Wa in place of x
3240000 / Wa x - ( 600 * 2x - 1800 ) / x = (1800 * x ) / ( x * 3 ) - 20
3240000 / (Wa * 1800/ Wa ) - ( (1200x - 1800) / (1800 / Wa ) = 580
......
324 * 10 ^ (4) - 2160000 + 1800Wa = 580 * 1800
1080000 + 1800Wa = 580 * 1800
Wa = (1080000 - 1044000 ) / 1800 = 20 tons
Where am i wrong?
A) 50
B) 200
C) 150
D) 100
E) 250
I found it to be a time and work question .
Wa = Team work rate original
Wb = Work rate when technical glitch was found .
x = No of days it took for the team to originally complete the work .
Wa * x = 1800 --(i)
x/3 * Wb = ( Wa * x/3 ) - 20 ---(ii) the team was able to achieve an output of 20 tons less than the planned output
y = 1800 - ( tons covered in 1/3 Days by team at a work rate of Wb ) --(iii)
Wa * (x - x/3) = y + 20 --(iv) the team overachieved for the rest of the days by 20 tons
Wa * ( (x - 1) - x/3 ) + ( Wb x ) / 3 = 1800 --(v) The end result was the team completed the task one day ahead of time
(vi)-- Tons covered in x/3 days = Wb * x/3
We see that
Wb x = 5400 - Wa (2x -3)
Wb = ( 5400 - Wa ( 2x -3) ) / x
x/3 * Wb = ( Wa * x/3 ) - 20 ---(ii)
Substituting Wb in (ii)
1800 / ( 3 Wa) * ( 5400 / x - Wa ( 2x -3) / x ) = ( Wa x ) / 3 - 20
600 / Wa * 5400 / x - ( 600/Wa * (Wa * ( 2x -3 ) ) / x ) = Wa x / 3 - 20
Substituting 1800 / Wa in place of x
3240000 / Wa x - ( 600 * 2x - 1800 ) / x = (1800 * x ) / ( x * 3 ) - 20
3240000 / (Wa * 1800/ Wa ) - ( (1200x - 1800) / (1800 / Wa ) = 580
......
324 * 10 ^ (4) - 2160000 + 1800Wa = 580 * 1800
1080000 + 1800Wa = 580 * 1800
Wa = (1080000 - 1044000 ) / 1800 = 20 tons
Where am i wrong?
Last edited: